State regulators want AmerenUE to disclose plans

Tuesday, January 31, 2006 | 12:00 a.m. CST; updated 10:55 a.m. CST, Wednesday, February 18, 2009

Missouri regulators have sided with a pair of state agencies and an environmental coalition that want utility company AmerenUE to more fully disclose its long-range plans.

Those plans could include construction of a second nuclear reactor at its Callaway County plant near Fulton, according to recent comments by Gary Rainwater, chief executive officer of St. Louis-based Ameren Corp., the utility’s parent company.

The five-member Missouri Public Service Commission, which regulates utilities, had previously honored AmerenUE’s December request that its 3,000-page Integrated Resource Plan be classified as “highly confidential,” a designation that restricts who sees the report.

But on Thursday, the PSC ordered AmerenUE to refile the plan by Feb. 10 but redact information it deems confidential. The two sides will then meet with the commission on Feb. 22 to negotiate a broader public release of information.

“It’s as much as we could have expected,” said attorney Henry Robertson of the Great Rivers Environmental Law Center in St. Louis.

The law firm represents four environmental groups that challenged the utility’s confidentiality request: Sierra Club, Missouri Coalition for the Environment, Mid-Missouri Peaceworks and the Association of Community Organizations for Reform Now.

In response to that challenge, AmerenUE acknowledged that portions of its long-range plan can be revealed. The utility offered to refile

redacted versions of a seven-page executive summary along with a 200-page section of the larger plan known as an Integrated Resource Analysis.

The utility considers the remaining 2,800 pages to contain largely technical data “of little interest or use to the general public,” according to the Jan. 26 PSC order.

Although one member dissented, a majority of the commission disagreed with that assessment.

Instead, the commission endorsed a suggestion by the state’s Office of Public Counsel, which advocates on behalf of Missouri utility customers, requiring AmerenUE to resubmit the entire document, minus those portions it considers confidential.

Public Counsel Lewis Mills Jr. called AmerenUE’s contention that reviewing the entire plan for sensitive information is too burdensome a “feeble protest.”

“To me, that’s not a valid reason,” he said Monday. “It may be a burden, but that’s too bad. That’s what it takes to be a public utility.”

A company spokesman said AmerenUE is working diligently to meet the state-imposed deadline.

“We have to go through all 3,000 pages and take out anything we consider proprietary,” said spokesman Mike Cleary. “The problem is the complexity of this document. It’s just a huge burden on staff.”

Also urging broader disclosure of AmerenUE’s plans was the state Department of Natural Resources, which in a filing with the commission called AmerenUE’s proposal for more limited disclosure “a good start” but one that “does not go far enough.”

Robertson called the support of DNR and the Office of Public Counsel critical.

“I think that was very important in getting us the decision we did,” he said. “If it was us alone, it would have been much more difficult.”

Cleary emphasized that any discussion of a possible second nuclear reactor at the Callaway plant is preliminary. Rainwater told a group of Columbia business leaders in December that the company was “seriously considering” such a move, which would be years away.

Cleary said the utility’s long-range plans also include renewed consideration of a second pump storage plant on Church Mountain near the Taum Sauk hydroelectric plant in southeast Missouri — a proposal that was scrapped in 2001 after environmental groups and state officials objected.

But even that measure remains uncertain, Cleary said, noting that the Integrated Resource Analysis was filed just days before the Dec. 14 collapse of the Taum Sauk plant’s reservoir.

“Our future plans are a moving target,” he said.

Mark Haim, of Mid-Missouri Peaceworks, said his group challenged the secrecy of AmerenUE’s long-range plans to ensure its expansion proposals are “not hidden from the public.” Peaceworks also wants to ensure that AmerenUE gives full consideration to more efficient utilization of energy and the generation of power from renewable sources.

Ken Midkiff, conservation chairman of the Ozark Chapter of the Sierra Club, said that group has been watching AmerenUE’s long-range plans since it learned a few years ago of the utility’s plan to create a hydro-electric plant atop Church Mountain that would be even larger than the similar and nearby Taum Sauk reservoir in southeast Missouri. Midkiff said such reservoirs amount to massive mountaintop “bathtub(s)” and destroy the landscape. In 2001, AmerenUE withdrew its application for a federal permit allowing the reservoir.

Missourian reporter Sean Sposito contributed to this report.


Like what you see here? Become a member.


Show Me the Errors (What's this?)

Report corrections or additions here. Leave comments below here.

You must be logged in to participate in the Show Me the Errors contest.


Comments

Leave a comment

Speak up and join the conversation! Make sure to follow the guidelines outlined below and register with our site. You must be logged in to comment. (Our full comment policy is here.)

  • Don't use obscene, profane or vulgar language.
  • Don't use language that makes personal attacks on fellow commenters or discriminates based on race, religion, gender or ethnicity.
  • Use your real first and last name when registering on the website. It will be published with every comment. (Read why we ask for that here.)
  • Don’t solicit or promote businesses.

We are not able to monitor every comment that comes through. If you see something objectionable, please click the "Report comment" link.

You must be logged in to comment.

Forget your password?

Don't have an account? Register here.

advertisements